UK HQ Your time

Metro Tunnelling Dewatering

Containerised Treatment Process for TBM slurry processing with 95% water recycle on a 12 km metro extension project.

Project Overview

A 12 km metro line extension beneath a major European capital, involving twin-bore tunnels with diameters of 6.2 m excavated by earth pressure balance TBMs. The project generated 450-600 m³/day of slurry water from TBM cutterhead lubrication, segment grouting, and groundwater inflow. Discharge to sewer was prohibited by the city's water authority, requiring full on-site treatment and recycle.

"Space was our biggest constraint — we had a 20 m × 40 m compound next to a live railway with no room for conventional civil works. The containerised plant arrived on flatbeds and was treating water within 48 hours of connection."

— Site Agent, Tunnel Construction JV

The Challenge

Tunnelling slurry presented a unique treatment challenge distinct from conventional wastewater:

  • High suspended solids: 8,000-25,000 mg/L TSS from bentonite, rock flour, and grout residues
  • High pH: Grout bleed water reaching pH 12.5, requiring neutralisation before advanced biological treatment
  • Variable chemistry: Transition from clay to sand to chalk geology changed slurry characteristics weekly
  • Space constraints: No room for permanent civil structures; treatment plant needed to move 3 times during project
  • Zero discharge requirement: All water to be recycled as TBM makeup or dust suppression

The Solution

Reynolds & Bauhm proposed a fully containerised, relocatable Treatment Process comprising four 40-foot high-cube shipping containers:

Container 1: Screening & Grit Removal

  • Coarse screen: 6 mm step screen for rock fragments and debris
  • Desanding cyclone: Hydrocyclone separator removing sand >75 µm at 95% efficiency

Container 2: Equalisation & pH Correction

  • 40 m³ balance tank: With submersible mixer and pH probe array
  • Automated acid dosing: HCl dosing to maintain pH 7.0-8.5 for downstream processes

Container 3: DAF & Lamella Clarification

  • QuickDAF unit: 50 m³/h capacity with integrated flocculation and flotation
  • Lamella clarifier: Polishing stage reducing TSS to < 50 mg/L
  • Chemical dosing: PAC and anionic polymer for colloidal clay removal

Container 4: Filtration & Disinfection

  • Self-cleaning filter: 100 µm automatic backwash filter protecting TBM pumps
  • UV disinfection: Medium-pressure UV for bacterial control (Legionella prevention)
Containerised QuickDAF
Lamella Clarifier
Self-Cleaning Filter
UV Disinfection

Results

Raw Slurry

  • TSS: 15,000 mg/L
  • pH: 11.5-12.5
  • Turbidity: 8,500 NTU
  • Conductivity: 3,200 µS/cm

Treated Recycle Water

  • TSS: 35 mg/L (99.8% removal)
  • pH: 7.2-7.8
  • Turbidity: 12 NTU
  • Conductivity: 3,150 µS/cm

Project Impact

MetricValue
Total water treated (project duration)285,000 m³
Water recycled to TBM270,750 m³ (95%)
Fresh water purchased14,250 m³ (5% makeup)
Estimated fresh water requirement avoided
Sludge disposed (dewatered)3,800 tonnes
Plant relocations3 (average 16 hours each)

Compliance & Environmental

The project maintained full compliance with the city's groundwater protection ordinance and construction site discharge regulations. Third-party water quality auditing confirmed zero uncontrolled releases to the urban sewer network or surrounding groundwater aquifer. The project received the client's annual sustainability award for water stewardship.

Key Learning

Containerised treatment is not merely a space-saving expedient — it fundamentally changes project logistics. By eliminating the need for civil construction at each worksite, the treatment plant moves with the TBM advance, reducing both capital cost and environmental permitting burden. The QuickDAF container format has since been adopted as standard for all tunnelling projects in the client's portfolio.

Related Case Studies

Brewery

Brewery DAF CFD Optimisation

CFD-guided contact zone redesign achieving 94% TSS removal and annual benefits.

Read Case Study
Mining

Mining Tailings Dewatering

Multi-disc screw press reducing tailings volume by 68% and enabling 85% water recycle.

Read Case Study
Desalination

SWRO Pre-Treatment DAF

Seawater DAF reducing TEP loading ahead of SWRO membranes, extending CIP intervals.

Read Case Study

Tunnelling Water Treatment

Containerised, relocatable treatment processes for TBM slurry, shaft dewatering, and construction runoff.

Industries We Serve

Our expertise spans multiple industries with sector-specific water treatment solutions.