UK HQ Your time

From Enquiry to Operational Plant in 6 Months — If You Run the Checklist

Honest Project Timeline With Hot-Climate Realities

A standard temperate containerised plant is typically operational 4–5 months from order. Hot-climate sites add 6–10 weeks because of: longer FAT/IAT due to the broader test envelope; specialist sea-freight logistics; permit/customs in many target jurisdictions; concrete-foundation lead time. This checklist runs through the steps that consistently catch out first-time customers.

Step 1 — Site Assessment (Week 0–2)

Before Any Equipment Is Specified

Geographical & Climate Data

Site coordinates (lat/long), ASHRAE 1 %/0.4 % design temperature, peak GHI, prevailing wind direction and speed, sand-storm frequency, last 10 years of flood records. Public sources for most of the world; bespoke survey only if data is sparse.

Feed Water Analysis

Full ionic balance (Na, K, Ca, Mg, Cl, SO4, HCO3, NO3, F, B, SiO2, total Fe, total Mn, NH4), TDS, conductivity, pH, alkalinity, total/calcium hardness, turbidity, SDI15, free chlorine, total chlorine, TOC, total bacteria count. Minimum 3 samples spread over 6–12 months. Without this, scaling indices cannot be calculated and recovery cannot be set.

Power Source & Site Power Quality

If grid power available: voltage, frequency, harmonics, fault current, RMU specification. Voltage stability is often poor at end-of-feeder remote sub-stations. If solar/diesel hybrid: solar resource (PVGIS / NSRDB / SAM), diesel fuel availability and scope, fuel storage permits.

Road Access & Crane Capability

Container truck access (width, weight limits, turning radius), crane availability for 12–20 t lift, local lifting permit/inspection regime. Some remote sites need on-site mobile crane hire weeks in advance.

Foundation Conditions

Soil type, bearing capacity, drainage, depth to water table, depth to bedrock. For container on slab, 80–100 kPa bearing is typical — well within most undisturbed soils but desert sand needs compaction or piling.

Discharge / Disposal Routes

Where does treated water go (storage tank, distribution main, reuse)? Where does concentrate/brine go (evaporation pond, sea outfall, deep-well injection)? Where do filter backwash and sludge go? Permit status of each.

Local Permits & Approvals

Water-abstraction licence, environmental permit, building permit for foundation, electrical compliance certificate, customs/import documentation. Some jurisdictions take 8–16 weeks for approvals — start in parallel with equipment design.

Step 2 — Process & Mechanical Design (Week 2–10)

Workshop-Side Engineering

Process Flow Diagram & Mass Balance

Treatment-train selection from feed analysis (see water-source guide), mass balance at design and turndown conditions, recovery and product-quality projections, chemical dosage calculations.

P&ID & Instrument List

Full P&ID with instrument tags, loop numbers, set points, alarms, interlocks. Hot-climate spec adds duplicate temperature transmitters on critical points (electronics cabinet, motor windings, oil-cooler outlets).

General Arrangement & 3D Model

3D layout inside the container including service access, valve operability, electrical clearances, HVAC discharge clear of intakes. Heat-dissipation CFD where load density is high — see CFD services.

Equipment Specifications & Datasheets

Each major item: pump curves verified at site-condition water temperature and viscosity, motor windings sized for site ambient, control panel cooling sized for cabinet temperature target, gasket material confirmed for site UV exposure.

SCADA Architecture & Comms

Local PLC, HMI, remote-monitoring satellite or 4G/5G link, cyber-security design. See SCADA integration. Critical: schedule a connectivity test from the actual site location — many "covered" 4G areas drop to GSM-only in practice.

Step 3 — Fabrication, FAT & IAT (Week 10–20)

Two Tests, Not One

Workshop Fabrication

Sandwich panels assembled into containerised shell; mechanical equipment installed; piping, electrical, instrumentation completed. Hot-climate-specific items: cool-roof coating applied, all cabinet seals checked, silicone gaskets fitted (not EPDM).

Factory Acceptance Test (FAT)

2–5 days of testing in our workshop with town-water simulation: hydraulic test, electrical tests, instrumentation calibration, control-loop validation, alarm verification, full operational sequence (start, normal run, shutdown, fault recovery). Customer witnessed. Defects fixed before shipping.

Hot-Climate Soak Test

Specific to hot-climate units — 48-hour run at our workshop in a temperature-controlled enclosure simulating 50 °C ambient. Verifies HVAC, electronics derating margin, control-system stability. Adds 1–2 weeks to schedule but catches issues before site shipping.

Shipping & Customs

Container sealed, lashed for road/rail/sea, all loose items pack-listed and shipped separately. Customs clearance can take 2–6 weeks depending on jurisdiction; many countries require a local sponsor / agent of record. Build into schedule.

Site Installation Acceptance Test (IAT)

On-site testing after installation: 5–10 days of operation on actual feed water, monitored against the FAT envelope. Performance guarantee (recovery, product quality, specific energy) demonstrated. Punch-list closed. Hand-over to customer operations.

Step 4 — Foundation & Civil Works (in parallel, Week 4–16)

Hot-Climate Foundation Specifics

Concrete Pad

200–400 mm reinforced concrete slab, raised 200 mm above grade to keep doors above any sand-drift. Steel embeds for container twist-lock fittings. Earthing grid embedded in foundation.

Lightning Protection & Earthing

Hot-climate sites are often exposed (no surrounding structures), so direct-strike lightning protection is essential. Air-termination above container, down-conductors to earth electrodes, surge-protection devices on all incoming power and signal lines.

Drainage

Sloped pad with perimeter drain. Even arid sites get the 1-in-30-year flash flood — without drainage the container floods.

Sand-Drift Mitigation

Foundation berm and sand-fence as covered in the dust & sand page.

Site Security

Perimeter fence, lockable access gate, security lighting on PV-stand-by power. Remote sites in some regions need cellular-monitored intrusion detection.

Step 5 — Commissioning & Hand-Over (Week 20–24)

From Hardware Delivery to Routine Operation

Mechanical Install

Container placed on foundation, services connected (power, feed water, treated water out, concentrate out, drains, communications). Pre-commissioning checks: hydraulic pressure test of new connections, electrical insulation tests, instrument loop checks.

Initial Flush & Disinfection

System flushed to remove construction debris and shipping preservatives, then chlorine disinfected (50–100 ppm, 30 min hold) and rinsed.

Cold Commissioning — No Water

All instruments calibrated and verified; all motors bumped for rotation; all interlocks tested; all alarms tested. SCADA full sweep.

Wet Commissioning — Town Water First

If available, town water through the plant first to verify hydraulics, control loops, and performance at known feed quality.

Process Commissioning — Real Feed

Switch to real feed water, dose chemicals, optimise antiscalant/coagulant dose by jar test or online analyser feedback. Membrane conditioning if RO.

Operator Training & Documentation

2–5 days of on-site training covering normal operation, alarm response, weekly/monthly/quarterly maintenance, spares ordering, escalation. All documentation (P&ID, O&M manual, electrical drawings, datasheets) handed over in hard-copy and PDF.

Performance Demonstration & Hand-Over

5–10 day continuous run demonstrating contractual performance guarantees. Punch-list closed; final acceptance certificate signed; warranty period begins. Hand-over to plant operations.

Step 6 — Operations & Aftercare

The First Year Matters Most

Spares Strategy

Recommended commissioning spares (consumables: cartridges, antiscalant, gaskets, filters — first 6 months); recommended operating spares (12-month consumables + insurance items: VFD, PLC CPU, transmitters). Held at site or at a regional bonded warehouse depending on shipping logistics.

Remote Support & SLA

24/7 telephone/email response from UK engineering; remote SCADA monitoring; agreed travel-response time for site visits (typically 5–14 days for hot-climate remote sites — honest about travel time, not guaranteed in 24h).

Local Agent / Service Partner

For sites > 5 days from the UK, we partner with a local service company for first-response. Local agent stocks immediate-need spares, performs scheduled maintenance, and escalates to us for major service.

Performance Monitoring & Reporting

Monthly performance report from SCADA data: throughput, recovery, product quality, energy consumption, alarm frequency. Annual on-site audit and report. Performance reports drive continuous-improvement and pre-empt failures.

Mid-Life Refurbishment

Year 4–5: HVAC service, recoat of cool-roof, membrane replacement (typical 4–6 yr life in hot service), VFD capacitor replacement, battery replacement if lead-acid (3–5 yr) or LFP (10+ yr).

Where to Read Next

Cross-Links Within the Hot-Climate Cluster

Ready to Run the Checklist?

We have a one-page hot-climate site-assessment form that gives us everything needed for a budget scope within ten working days. Ask for it.

Industries We Serve

Our expertise spans multiple industries with sector-specific water treatment solutions.