Example ApplicationOil & Gas

Produced Water Treatment for Reuse

This is an illustrative scenario showing how Reynolds & Bauhm equipment can be configured for this application. Every site has unique requirements — contact us for a solution tailored to your specific wastewater characteristics.

Process Requirements & Constraints

Onshore oil field producing 500 m3/day of produced water with oil 150 mg/L, TDS 12,000 mg/L, H2S 25 mg/L, and suspended solids 300 mg/L. Client requires treated water with oil <5 mg/L for reinjection to maintain reservoir pressure. Water recovery target 65%.

Key Performance Targets
<5
Oil mg/L
<500
TDS mg/L
65%
Water recovery
<0.5
H2S mg/L
<100
CFU/100mL
24/7
Automatic operation

Treatment Approach

Step-by-step process configuration from raw wastewater to compliant discharge.

01

CPI Separation

Corrugated Plate Interceptor (CPI) separator removes free oil and large solids. 45-minute retention, plate spacing 20 mm. Oil skimmer recovers crude for resale. Effluent oil reduced to 45 mg/L.

02

Induced Gas Flotation

IGF unit with microbubble generation removes emulsified oil to <10 mg/L. Automated chemical dosing of demulsifier and flocculant optimises oil bubble attachment and separation.

03

DAF Polishing

DAF system provides final oil removal achieving <5 mg/L. Coagulant and polymer dosing ensures fine oil droplet capture. Skimmings returned to CPI separator.

04

Reverse Osmosis

Spiral-wound RO membranes desalinate DAF effluent from 12,000 to <500 mg/L TDS. Two-pass configuration with energy recovery. 65% water recovery, 35% brine to evaporation pond.

05

H2S Stripping & Disinfection

Packed column air stripping removes H2S from <0.5 mg/L. UV disinfection ensures <100 CFU/100mL for reinjection. SCADA-controlled automatic operation.

Equipment Configuration

The specific equipment selected for this application, sized for the flow rate and contaminant load.

CPI Separator

Carbon steel with internal coating, 100 m3/h capacity, automatic oil skimmer, sludge pump.

View Equipment

DAF System

High-rate DAF for produced water, 60 m3/h, 600 kPa saturation, SS construction with coating.

View Equipment

RO Skid

Two-pass SWRO, 8-inch vessels, 65% recovery, energy recovery device, CIP system.

View Equipment

UV Disinfection

Medium-pressure UV, 40 mJ/cm2 dose, automatic wiper, UV intensity monitoring.

View Equipment

Performance Achieved

Representative performance data based on typical operating conditions for this equipment configuration.

<5
Oil mg/L
<500
TDS mg/L
65%
Water recovery
<0.5
H2S mg/L
<100
CFU/100mL
24/7
Automatic operation

Related Equipment

Explore the full range of equipment used in this and similar applications.

Chemical Dosing System

Coagulant, flocculant, and demulsifier dosing for oil separation.

View Equipment

pH Correction

Acid/alkali dosing for RO feed pH optimisation and scale control.

View Equipment

Cartridge Filter

5-micron RO pre-filtration to protect membranes.

View Equipment

Progressive Cavity Pump

Reliable high-pressure feed pump for RO system.

View Equipment

Related Treatment Processes

Discover how these treatment processes connect to form complete wastewater treatment solutions.

Project Approach & Engineering

Reynolds & Bauhm follows a structured engineering methodology for every project. We begin with detailed wastewater characterisation, process selection based on contaminant profiles, pilot testing where required, and full-scale design with performance guarantees. Our multidisciplinary team of chemical, mechanical, and electrical engineers ensures seamless integration of process, mechanical, and control disciplines.

Characterisation

Comprehensive influent analysis including COD, BOD, TSS, heavy metals, pH, temperature, and flow profiling.

Process Design

Process flow development with P&IDs, mass balances, and hydraulic modelling validated by CFD where appropriate.

Pilot Testing

On-site pilot trials validate performance guarantees under actual operating conditions before capital commitment.

Commissioning

FAT, SAT, performance trials, operator training, and handover documentation ensuring operational readiness.

Equipment Configuration

Pre-TreatmentScreening, grit removal, and flow equalisation
Primary TreatmentDAF or lamella clarification for solids and oil removal
Secondary TreatmentBiological oxidation (activated sludge, MBBR, or SBR)
Tertiary TreatmentFiltration, UV disinfection, or chemical polishing
Sludge ManagementThickening and dewatering via belt press or centrifuge
Control SystemPLC with HMI touchscreen and optional SCADA integration
Chemical DosingAutomated coagulant, flocculant, and pH correction
MaterialsSS316L, duplex, or rubber-lined carbon steel

Performance Outcomes

COD Removal

85 – 98% chemical oxygen demand reduction depending on process configuration and influent variability.

TSS Removal

90 – 99% suspended solids reduction through combined physical and biological treatment stages.

Water Reuse

Tertiary treatment enables up to 80% water recycling for non-potable process applications.

Apply This Configuration to Your Site

Our engineers will adapt this equipment configuration to your specific wastewater analysis, flow rate, and discharge requirements.