UK HQ Your time

Performance & Reliability Testing

Commissioning, FAT & SAT — in depth

The final gate is performance. The plant is run at design flow and load over a defined test period, with witnessed sampling against the contractual guarantees and a reliability run to prove stable, continuous operation — the objective basis for plant acceptance and handover.

Performance Run

What matters in practice

Design-Load Run

Plant at full flow and load.

Witnessed Sampling

Effluent against guarantees.

Reliability Period

Stable continuous operation proven.

Acceptance

Objective pass criteria.

Performance Criteria

ItemBasisEvidence
ThroughputDesign flowRecords
QualityGuaranteeLab
ReliabilityTest periodLogs
Power/chemDesignConsumption

Related Topics

Continue across this series

Talk to our engineers

Reynolds & Bauhm designs and delivers commissioning, fat & sat solutions backed by process engineering and performance guarantees.

Performance & Reliability Testing: Engineering Detail

Fundamentals, design drivers and practical guidance

Commissioning performance testing — running the plant at design load over a defined period to demonstrate it meets its guaranteed throughput and quality.

A Factory Acceptance Test verifies the panel, PLC and software against the functional design specification before it leaves the factory: I/O is simulated, interlocks and trips are forced, alarms and sequences are demonstrated, and the client witnesses and signs off. Site Acceptance Test then repeats the critical checks in situ, confirming that field wiring, instruments and final elements behave as the tested logic expects once connected to real plant.

Loop checking is the systematic, point-by-point proof that every instrument signal travels correctly from field to control system and every output drives the right final element, in the right direction, with the right scaling. Only when loops are proven does performance testing begin — running the process against its guaranteed duty (flow, removal efficiency, energy) over a defined period to demonstrate the contract is met before handover.

Reynolds & Bauhm runs structured FAT and SAT regimes, full loop-check documentation and witnessed performance tests, so plants are handed over proven against specification with a complete, auditable commissioning record — not signed off on optimism.

Design & Specification Considerations

What our engineers assess on every scope of this type

  • I/O simulation, forced interlocks and demonstrated trip actions
  • SAT confirming field wiring and final elements after installation
  • Point-by-point loop checks: signal path, direction and scaling
  • Cause-and-effect / interlock verification before energising plant
  • Performance test against guaranteed duty over a defined run
  • Punch-list management and close-out to sign-off
ParameterTypical basisWhy it matters
SATRepeated on siteProves field wiring and instruments
Loop checkEvery signal, point by pointConfirms path, direction and scaling
InterlocksCause-and-effect testedSafety functions proven before run
Performance testAgainst guaranteed dutyDemonstrates the contract is met
DocumentationSigned records per stageAuditable basis for handover
FATWitnessed at supplier worksCatches logic/panel faults early and cheap

Frequently Asked Questions

Common questions on installation and commissioning

How is plant performance demonstrated?

Through a witnessed performance test running the process against its guaranteed duty — flow, removal efficiency and energy — over an agreed period. Meeting the targets over that run is the basis for acceptance and handover.

What documentation is produced?

A complete commissioning pack: FAT and SAT records, loop-check sheets, interlock cause-and-effect results, the performance-test report and a closed punch list — an auditable trail that the plant was proven, not assumed.

Why test at FAT before delivery?

Because a fault found in the supplier's works during Performance & Reliability Testing-type checks is far cheaper and faster to correct than the same fault discovered during live commissioning on site. FAT proves the panel, logic and sequences against specification before anything ships.

What is the difference between FAT and SAT?

FAT verifies the control system in the factory with simulated I/O; SAT repeats the critical checks on site once the panel is wired to real instruments and final elements. SAT confirms that the proven logic still behaves correctly with field reality connected.

Industries We Serve

Our expertise spans multiple industries with sector-specific water treatment solutions.

Related Pages

Explore closely-related topics, equipment and guides