UK HQ Your time

Site Acceptance Testing (SAT)

Commissioning, FAT & SAT — in depth

SAT proves the plant works where it matters. After installation, the system is tested on site with real power, water, instruments and interfaces — confirming installation quality, I/O, control sequences and safety functions against the SAT protocol — the gate between construction and live operation.

SAT Scope

What matters in practice

Services Connected

Power, water and air verified.

I/O & Interfaces

Field I/O and DCS links checked.

Control Sequences

Automatic sequences proven.

Safety Functions

Interlocks and trips tested.

SAT Elements

ElementChecksNote
ServicesConnectedVerified
I/OField/DCSLoop-checked
SequencesAutomaticProven
SafetyInterlocksTested

Related Topics

Continue across this series

Talk to our engineers

Reynolds & Bauhm designs and delivers commissioning, fat & sat solutions backed by process engineering and performance guarantees.

Site Acceptance Testing (SAT): Engineering Detail

Fundamentals, design drivers and practical guidance

Site acceptance testing (SAT) — verifying the installed plant operates correctly on site with real services, instruments and interfaces before start-up.

Commissioning is the disciplined transition from a constructed plant to a proven, operating one, and it is split into clear stages: Factory Acceptance Test (FAT), Site Acceptance Test (SAT), loop checking, and performance testing. Each stage de-risks the next — faults caught at FAT in the supplier's works are an order of magnitude cheaper to fix than the same fault found during live process commissioning on site.

A Factory Acceptance Test verifies the panel, PLC and software against the functional design specification before it leaves the factory: I/O is simulated, interlocks and trips are forced, alarms and sequences are demonstrated, and the client witnesses and signs off. Site Acceptance Test then repeats the critical checks in situ, confirming that field wiring, instruments and final elements behave as the tested logic expects once connected to real plant.

Loop checking is the systematic, point-by-point proof that every instrument signal travels correctly from field to control system and every output drives the right final element, in the right direction, with the right scaling. Only when loops are proven does performance testing begin — running the process against its guaranteed duty (flow, removal efficiency, energy) over a defined period to demonstrate the contract is met before handover.

Design & Specification Considerations

What our engineers assess on every scope of this type

  • Cause-and-effect / interlock verification before energising plant
  • Performance test against guaranteed duty over a defined run
  • Punch-list management and close-out to sign-off
  • Complete, auditable commissioning documentation pack
  • FAT against the functional design specification with the client witnessing
  • I/O simulation, forced interlocks and demonstrated trip actions
ParameterTypical basisWhy it matters
Performance testAgainst guaranteed dutyDemonstrates the contract is met
DocumentationSigned records per stageAuditable basis for handover
FATWitnessed at supplier worksCatches logic/panel faults early and cheap
SATRepeated on siteProves field wiring and instruments
Loop checkEvery signal, point by pointConfirms path, direction and scaling
InterlocksCause-and-effect testedSafety functions proven before run

Frequently Asked Questions

Common questions on installation and commissioning

Why test at FAT before delivery?

Because a fault found in the supplier's works during Site Acceptance Testing (SAT)-type checks is far cheaper and faster to correct than the same fault discovered during live commissioning on site. FAT proves the panel, logic and sequences against specification before anything ships.

What is the difference between FAT and SAT?

FAT verifies the control system in the factory with simulated I/O; SAT repeats the critical checks on site once the panel is wired to real instruments and final elements. SAT confirms that the proven logic still behaves correctly with field reality connected.

What does loop checking prove?

That each instrument's signal reaches the control system at the correct value, and each output drives the correct final element in the correct direction with the correct scaling. It is the foundation that performance testing relies on.

How is plant performance demonstrated?

Through a witnessed performance test running the process against its guaranteed duty — flow, removal efficiency and energy — over an agreed period. Meeting the targets over that run is the basis for acceptance and handover.

Industries We Serve

Our expertise spans multiple industries with sector-specific water treatment solutions.

Related Pages

Explore closely-related topics, equipment and guides