Example ApplicationTextile Industry

Textile Dye House Effluent Decolorization

This is an illustrative scenario showing how Reynolds & Bauhm equipment can be configured for this application. Every site has unique requirements — contact us for a solution tailored to your specific wastewater characteristics.

Process Requirements & Constraints

Woven fabric dye house discharging 600 m3/day of reactive dye wastewater with colour 1,500 Pt-Co units, COD 3,200 mg/L, BOD 1,100 mg/L, and sulphide 45 mg/L. Must meet sewer discharge limits of colour <100 Pt-Co, COD <500 mg/L, and eliminate sulphide odour.

Key Performance Targets
<50
Colour Pt-Co
180
Final COD mg/L
<0.5
Sulphide mg/L
94%
Colour removal
100%
Odour elimination
<100
Sewer limit met

Treatment Approach

Step-by-step process configuration from raw wastewater to compliant discharge.

01

Screening & Equalization

0.5 mm rotary screen removes fibre and lint. 18-hour equalization with automated pH adjustment to 7.0. Flow and load balancing between dyeing batches.

02

Coagulation-Flocculation

Ferric chloride (200 mg/L) and anionic PAM dosed via rapid mix and flocculation chambers. Colour reduced to 400 Pt-Co. Dye molecules destabilised and aggregated for flotation removal.

03

DAF Colour Removal

Dissolved air flotation removes coagulated dye particles as float sludge. Surface skimmer transfers coloured float to thickening tank. DAF effluent colour <150 Pt-Co, TSS <40 mg/L.

04

Ozonation decolourisation

Ozone generator producing 1.5 kg O3/h contacts DAF effluent in 15-minute reaction column. Residual colour destroyed by direct ozone oxidation. Final colour <50 Pt-Co. Sulphide oxidised to sulphate eliminating odour.

05

Final Polishing

Biological sand filter provides final COD polishing from 350 to 180 mg/L. Backwash wastewater returned to equalization. Effluent meets all sewer discharge parameters consistently.

Equipment Configuration

The specific equipment selected for this application, sized for the flow rate and contaminant load.

DAF System

Rectangular DAF, 35 m3/h, ferric/PAM dosing, colour-optimised flotation, automatic scraper.

View Equipment

Ozone Generator

Corona discharge, 1.5 kg O3/h, oxygen feed, ozone destructor, residual ozone monitor.

View Equipment

Chemical Dosing Skid

Ferric chloride day tank, PAM make-up unit, dosing pumps, flow-paced control.

View Equipment

Sand Filter

Gravity sand filter, 1.5 m diameter, 6 m/h filtration rate, automatic backwash.

View Equipment

Performance Achieved

Representative performance data based on typical operating conditions for this equipment configuration.

<50
Colour Pt-Co
180
Final COD mg/L
<0.5
Sulphide mg/L
94%
Colour removal
100%
Odour elimination
<100
Sewer limit met

Related Equipment

Explore the full range of equipment used in this and similar applications.

pH Correction System

Automated acid/alkali dosing for equalization and reaction pH control.

View Equipment

Sludge Thickener

Thickening of DAF float sludge before disposal.

View Equipment

Online Colour Meter

Spectrophotometric colour monitoring for process control.

View Equipment

Screening Equipment

Fine screening for fibre and lint removal from textile wastewater.

View Equipment

Related Treatment Processes

Discover how these treatment processes connect to form complete wastewater treatment solutions.

Project Approach & Engineering

Reynolds & Bauhm follows a structured engineering methodology for every project. We begin with detailed wastewater characterisation, process selection based on contaminant profiles, pilot testing where required, and full-scale design with performance guarantees. Our multidisciplinary team of chemical, mechanical, and electrical engineers ensures seamless integration of process, mechanical, and control disciplines.

Characterisation

Comprehensive influent analysis including COD, BOD, TSS, heavy metals, pH, temperature, and flow profiling.

Process Design

Process flow development with P&IDs, mass balances, and hydraulic modelling validated by CFD where appropriate.

Pilot Testing

On-site pilot trials validate performance guarantees under actual operating conditions before capital commitment.

Commissioning

FAT, SAT, performance trials, operator training, and handover documentation ensuring operational readiness.

Equipment Configuration

Pre-TreatmentScreening, grit removal, and flow equalisation
Primary TreatmentDAF or lamella clarification for solids and oil removal
Secondary TreatmentBiological oxidation (activated sludge, MBBR, or SBR)
Tertiary TreatmentFiltration, UV disinfection, or chemical polishing
Sludge ManagementThickening and dewatering via belt press or centrifuge
Control SystemPLC with HMI touchscreen and optional SCADA integration
Chemical DosingAutomated coagulant, flocculant, and pH correction
MaterialsSS316L, duplex, or rubber-lined carbon steel

Performance Outcomes

COD Removal

85 – 98% chemical oxygen demand reduction depending on process configuration and influent variability.

TSS Removal

90 – 99% suspended solids reduction through combined physical and biological treatment stages.

Water Reuse

Tertiary treatment enables up to 80% water recycling for non-potable process applications.

Apply This Configuration to Your Site

Our engineers will adapt this equipment configuration to your specific wastewater analysis, flow rate, and discharge requirements.